A Consultant for Cloud Kicks notices that the Deploy date for the Sales Cloud project is also the same weekend of a Salesforce release.
What should the Consultant recommend?
- A . Stop all work because the impact of the Salesforce release is unknown
B. Let Cloud Kicks know that there is a Salesforce release and that it may take longer
C. Complete the project sooner and push before the Salesforce release
D. Update the project plan for the following week and communicate the change
Suggested Answer: D