Which of the following pre-requisites must be met for the system to check the shelf life of the materials at goods receipt? Note: There are 3 correct answers to this question.
- A . The Shelf life expiration date is activated for the plant in Customizing
B. The Purchase order item contains the remaining shelf life
C. Batch management is active for the material in the plant
D. The shelf life expiration date check is activated for the material type in Customizing
E. The shelf life expiration date check is activated for the movement type in Customizing
Suggested Answer: A,C,E