What are the consequences if the Dispatched operation status is set for a production order operation?
- A . You can reschedule the operation using midpoint scheduling in a planning table.
B. You can reschedule the operation using finite scheduling in planning table
C. You can reschedule the operation using lead time scheduling in a planning table
D. You can reschedule the order using infinite scheduling in a planing table
Suggested Answer: B,C