How is the actual availability of a resource for project assignments calculated?
- A . Available hours = Staffed hours - Free hours
B. Free hours = Available hours - Staffed hours
C. Free hours = Staffed hours - Available hours
D. Available hours = Free hours - Staffed hours
Suggested Answer: B